A bigger and more efficient plant

Construction of a new water treatment plant for more efficiency.

The François-Duroy plant is capable of treating 30,000 m³ of water per day and 1,500 m³ per hour.  It has three separate processing lines, which guarantees increased security.  The plant has a storage area of 7,500 m³.

It is equipped with new processing technologies.  An activated carbon reactor that traps all impurities present in the water, or membrane ultrafiltration that sends water into membranes at very high pressure, ensuring a very high quality filtration.

Key figures:

Production capacity:  1,500 m3/hour of treated water
720 tonnes of steel
7,500 m3 of concrete

Le projet en image

4 photos
Année
2018
Métier
Construction
Secteur d'intervention
Industry
Cycle de vie
Works & Construction
Travaux
depollutionasbestos disposalcladdingcivil workstructural work
Maître d'œuvre
Groupement Cabinet BOURGOIS / Cabinet MERLIN / COMPÈRE Selarl Architectes / BIENVENU Architectes
Maître d'ouvrage
RÉSEAU – Syndicat Mixte de Production d'Eau potable de la Région de Caen (SYMPERC)